Lees Corner Elementary Capital Project
Information about the Renovations
The Lees Corner Elementary project was identified according to the Renovation Queue, approved in 2009. Lees Corner ES is ranked 48 of 63 schools in the queue. Renovation with additions will bring the total building area to approximately 108,000 SF. The project adds approximately 26,000 square feet.
This is an exciting opportunity for our school and community as we improve our current school building and have several additions.
Key Details:
- New 2-story classroom addition
- New Gymnasium
- Main entry addition
- Cafeteria Addition
- Complete renovation of existing building spaces
Project Scope: Complete renovation and reorganization of the existing building, including demolition of interior and non-bearing walls. New academic addition of 2-story classroom addition, expanded and renovated gymnasium, administration addition - single story main administration suite and main entrance addition, expanded cafeteria including a new kitchen, reconfigured and renovated library, new playgrounds, and an outdoor classroom.
We are pleased to inform you the contract for the construction of our renovation and addition for our elementary school was approved by the school board as part of the consent agenda at the January 9, 2025 school board meeting. This milestone marks the beginning of an exciting new chapter for the Lees Corner Elementary School community. FCPS is thrilled to see this important project move forward. Henley Construction Company, Inc. was selected through a competitive bidding process. Construction value is $39,074,000.00. Henley is currently finishing construction at Louise Archer Elementary School and has successfully completed multiple FCPS projects. Henley is committed to completing the renovation and addition to on time and within budget. Construction is expected to begin later this month, with an anticipated substantial completion date of July 30, 2027. We understand that construction can bring about temporary changes, including temporary learning classrooms, noise, and traffic adjustments, and we appreciate your patience and understanding as the project progresses. We will continue to keep you updated with important milestones and any changes that may impact the surrounding community. A pre-construction community meeting will be held later this month. The meeting date is to be determined. We appreciate your patience and continued support as we work to improve our school facilities.
We appreciate your patience and support as we work to improve our school facilities. Stay tuned for more updates
Latest Update: January 10, 2025
Construction Information
ADA-accessible temporary classrooms and restrooms learning complex installed. Temporary education village fenced enclosure complete. New utilities for temporary education village are complete
- Phased Occupied Building: Students and Construction activities and workers are separated.
- Additional classrooms
- Renovated classrooms
- Sustainability Improvements: The renovation will feature a more sustainable building with all LED lighting and advanced lighting controls.
- HVAC System: A new, more efficient HVAC system with updated controls will enhance comfort and energy efficiency.
- Technology Upgrades: We are incorporating updated technology to support modern learning environments.
- Life Safety Upgrades: New fire alarm system, new security system, fire sprinkler system, and new generator.
- Water Conservation: Automatic low-flow sinks, toilets, and urinals will be installed to promote water conservation.
- Daylighting: New windows and improved natural lighting in classrooms and gymnasium.
- Kitchen and Expanded cafeteria: All new kitchen equipment and expanded cafeteria.
- Relocated and Improved: SACC, Library, music, and art.
- Various site improvements:
- New pre-K playground
- New school-age playground
- New outdoor basketball courts
- Improved kiss and ride circulation
- Additional parking
Lees Corner School Renovation Gallery
Future Events
Information on future engagement opportunities will be posted as soon as they are planned.
Pre-Construction Meeting
Date: Thursday, January 30, 2025
Time: 6:30–7:30 p.m.
Location: Lees Corner Elementary - Cafeteria
Language interpretation services will be available.
For updates, join the FCPS News You Choose subscription for this project. Once signed up or logged in, choose the Capital Projects (School Construction) and the school's construction topic.
Key Build Information
Funding: 2021 Bond (Planning/Design), 2023 Bond (Construction)
Future Building Area: 114,063 SF
Anticipated Future Capacity: 900 students
Building Area: 81,843 SF
Acreage: 13.9
Prior Renovation: n/a
Prior Capacity Enhancement: n/a
Renovation Queue Rank: #48
Architect: Grimm+Parker
Contractor: TBD
Current Status: Construction
Bid Opening Date: December 11, 2024
School Board Award Date: January 9, 2025 (anticipated)
Estimated Start of Construction: January 2025
Estimated Completion: Summer 2027
School Information
Address: 13500 Hollinger Ave, Fairfax, VA 22033
FCPS Region: 5
Grades: K-6
HS Pyramid: Chantilly HS
MS Feeder: Franklin MS
Opened: 1987
Programs: AAP Local Level IV, Autism, Intellectual Disabilities, SACC (1 classroom)
Past Engagement, Planning & Construction Information
October 4, 2023: Fairfax County Planning Commission Meeting
July 17, 2023 7:00 p.m.: Sully District Land Use Committee Meeting
- Address:
Sully District Governmental Center
4900 Stonecroft Blvd.
Chantilly VA 20151 - Presentation (July 2023)
March 29, 2023: Community Meeting
September 22, 2022: Design Feedback and Engagement Committee meeting #2
May 26, 2022: Design Feedback and Engagement Committee meeting #1